About the concrete mixing station installation matters on the foundation

2014-04-19

There are a lot of key parts needed we pay attention during Installation of concrete mixing station. If we do not notice one key, a small concrete mixing station will be not installed successfully which affect the production of the concrete batching station. Today we explain to everybody when installed on concrete mixing station foundation matters needing attention.

concrete mixing station
1. In the foundation, may not arbitrarily change the foundation the size of the figure above, if any changes, must and factory engineers to discuss it.
2. When mining base, with reinforced or peg reserved centerline, Labeling requirements clearly.Two of the same basic embedded iron centerline position to be in the same line, deviation shall not be greater than 20 mm.
3. When making baseline, lime sprinkled on the fixed line. The gap between lime thread must not exceed 50 mm.
Requirements in concrete batching plant foundation laid mat reinforcement, steel anchor shall not be less than the required size in drawing. The width and depth of foundation needed for mining shall not be less than the required size in drawing.
If you have any problems about Concrete mixing station foundation installation, please contact us freely, our engineers will help you solve your problem.
 